Under constructionTruro · Nova Scotia

Six units under construction in Truro.

Backfill began 23 September. Slab poured 21 October. Wall and floor panels craned in 27 to 29 October. Roof trusses up by 3 November.

The street side late in the day, the band between the floors sheathed and no daylight left in the upper openings
Mon 9 Nov, 16:02 Sheathing
Truro · 6 units

Two storeys in three days.

47 days from the backfill to 9 November. The wall and floor panels came from a Nova Scotia plant; the roof trusses stood thirteen days after the slab.

Where it stands
Mon 9 Nov Two storeys are framed and wrapped, the 41 roof trusses stood within two working days of arriving, the gables are sheathed, and the band between the floors is closed in.
Next
Roofing and siding, then the windows and the interior walls upstairs.

From above and inside 11 Nov

From the air and inside the frame.

From the air 11 Nov, in 12 secondsThe roof deck sheathed and the walls wrapped, in the building's block.
  1. The building from above on 11 November, from the street side: the sheathed roof deck with its bay over the street end, the wrapped walls with their window openings cut, the neighbours' roofs on three sides
    From the air 11 NovThe bay over the street end, and the neighbours on three sides.
  2. The street side from the air on 11 November, closer: the window and door openings cut through the wrap on both floors, the floor band exposed under the roof deck, the neighbours' houses beyond
    From the air 11 NovThe street side, closer: the openings cut, the floor band exposed under the deck.
  3. The lot from straight above on 11 November: the sheathed roof deck with its stepped bay toward the street, the gravel yard beside it, the neighbours' houses across the street at the top of the frame
    From the air 11 NovThe lot from straight above: the sheathed roof deck and the bay toward the street.
  4. Inside on 11 November: the ground floor under the second floor's trusses, the studs and the sheathing, a person in a hard hat seen from behind looking up
    Inside 11 NovThe ground floor under the second floor's trusses.
  5. Inside on 11 November: a floor plan on a phone held up to a window opening, the neighbour's yard beyond the studs
    Inside 11 NovThe floor plan on a phone, held up to a window opening.
The street side of the building: two storeys under twin gables, dark cladding with wood-tone panels, planting along the walk
As designed Rendering, October 2026The street side as drawn for construction: two storeys under twin gables, dark cladding with wood-tone panels.
The building from the street corner, the long side running back with the second-floor walkway
As designed Rendering, October 2026From the street corner: the long side running back, the terrace over the entry wing.
The building from the other corner, the entrances along the side
As designed Rendering, October 2026From the other corner: the entrances along the side, the walk running back to the parking.
The front and side from above the street
As designed Rendering, October 2026From above the street: the roof, the gables and the long side.
The roof and rear yard from above, the parking spaces at the back
As designed Rendering, October 2026From above the rear: the roof, the second-floor walkway along the long side, the parking behind.
The side walk to the entrances with the outside stair to the second floor
As designed Rendering, October 2026The side walk to the entrances, with the outside stair to the second floor.

1 / 6

The rear and side walls late in the day, the upper openings dark now that the roof above them is closed in

Sheathing

Day 47

Mon 9 Nov, 16:06

The band between the two floors closed in with sheathing on the rear and the street side by midday; by 16:00 no daylight shows through the upper openings, so the roof above them is closed in.

    15 / 15

    1. Backfill

      23 to 30 Sep
      1. An excavator starting the backfill around the foundation walls, the trench still open along the near side
        Day 0 Wed 23 Sep, 12:01The backfill begins: the excavator on the far side of the walls, the trench still open on the near side.
      2. Foundation walls with the gravel base between them, seen from the rear of the lot
        Day 7 Wed 30 Sep, 16:00The gravel base in place between the walls, ready for the plumbing.
    2. Under-slab plumbing

      6 to 7 Oct
      1. The under-slab pipe stubs standing in the gravel between the foundation walls, seen from the rear
        Day 14 Wed 7 Oct, 16:04The pipe stubs stand in the gravel between the walls. The inspections passed.
    3. The slab

      19 to 26 Oct
      1. The slab ready for the pour: insulation, vapour barrier, heating pipe and wire mesh laid between the walls
        Day 27 Tue 20 Oct, 14:38Ready for the pour: the plumbing stubs up through insulation, vapour barrier, heating pipe and mesh.
      2. The ground-floor slab, poured that morning, at the right of the rear yard
        Day 28 Wed 21 Oct, 16:00Poured that morning.
      3. The crane set up behind the slab the day before the panels, the first packs of lumber on the slab
        Day 33 Mon 26 Oct, 16:47The crane set up behind the slab the day before the panels, the first packs of lumber on it.
    4. Panels

      27 to 29 Oct
      1. Wall panels stacked on the slab on the morning of the first panel day
        Day 34 Tue 27 Oct, 09:30The ground-floor wall panels, stacked on the slab.
      2. The first ground-floor wall panels standing on the slab at the end of panel day one, the crane boom above
        Day 34 Tue 27 Oct, 16:42The same afternoon: the first ground-floor walls stand, braced, under the crane.
      3. A floor panel being lowered onto the ground-floor walls
        Day 35 Wed 28 Oct, 14:30One of the 12 floor panels of the second floor is lowered into place.
      4. Second-floor wall panels standing above the floor panels at the corner
        Day 36 Thu 29 Oct, 16:00The second-floor walls stand.
    5. Roof trusses

      30 Oct to 3 Nov
      1. Two storeys of wrapped wall panels at the corner, window openings cut, a truck at the side
        Day 37 Fri 30 Oct, 10:19Two storeys of wrapped wall panels, the window openings cut.
      2. Roof trusses standing overhead, seen from inside the second floor
        Day 40 Mon 2 Nov, 17:12The roof trusses overhead, from inside the second floor.
      3. Roof trusses standing along the building and the rear gable sheathed
        Day 41 Tue 3 Nov, 16:00Trusses along the building. The rear gable is sheathed.
    6. Sheathing

      From Fri 6 Nov
      1. Both storeys from the street with roof trusses visible through the upper openings
        Day 44 Fri 6 Nov, 16:00From the street: both storeys, the trusses behind the upper openings.
      2. The street side with the band between the floors sheathed and bracing at the corner
        Day 47 Mon 9 Nov, 12:00The band between the floors closed in.
      3. The street side late in the day, the band between the floors sheathed and no daylight left in the upper openings
        Day 47 Mon 9 Nov, 16:02By four in the afternoon the upper openings are dark: the roof above them is closed in.
    27 Oct to 3 Nov in 11 secondsThe wall panels set and the roof trusses standing.

    1 / 21

    Days are counted from the start of the backfill on 23 September. Source: the job record and the site cameras. measured As of Nov 9, 2026.

    How we build

    We run the build ourselves.

    We buy the materials, hire the trades and manage the site.

    The owner of the building sees the daily log from the site, the cameras, and the open book: every invoice theirs to read, against a maximum price stated before the build starts.

    The method

    Panels or framing, one building at a time.

    Helio picks the method for each building on its case. The Truro building went up as panels; the Halifax building is framed on site.

    What decides it: whether a crane can reach the lot, the season, the plant's schedule, and the price each way.

    1. Panels Walls and floors from a Nova Scotia plant, set by crane; two storeys in days on a tight lot.
    2. Site framing A local crew, the trusses supplied; the shell in weeks.
    The ER-3 programme · as of 15 October 2026

    A six and an eight in Dartmouth.

    Built by Kulak Construction on single ER-3 lots, each on the municipal record.

    The walk

    Come and see one.

    A capital partner starts with a call, then a walk through the Truro building. An owner of an ER-3 lot starts with the reading of the lot.