The Halifax Brief · Week of June 22–28, 2026
1 move; 21,002 units under construction.
The weekly read on Halifax development — the pipeline, rates, and policy, from the primary record.
Meanwhile, groundbreakings remained at zero units, leaving the city's construction activity concentrated among the 21,002 units already underway. The planning queue continues to hold 131 open applications, with a median wait time of 39 weeks. Against this backdrop, the 5-year GoC rate sits at 3.02%, down 34 basis points over the last 30 days, while CPI registered at 3.2%.
The pipeline ≥5 units · from the permit record
What actually moved
1 tracked move this week (-10 vs prior). 21,002 units are under construction.
Read from the permit record, deduplicated into tracked projects and dated: see the map
- Broke ground -3 WoW 0 · —
- Completed -1 WoW 1 · —
- Approved 0 WoW 0 · —
- Filed -6 WoW 0 · —
The standing pipeline, by stage
Where it happened
Rates & money
The cost of money, this week
Supply & demand
Starts, rents, vacancy
Halifax saw 5,859 multi-unit starts in 2025, a record 51% increase, as vacancy rose to 2.7% and two-bedroom rents grew 6.7% to $1,650.
People
The demand side
Halifax's population was 517,115, up 1,098 over the year (Statistics Canada).
Cost to build
The cost stack
Policy & programs
The capital stack & the rules
Planning watch · the queue
How long the planning queue runs
Halifax currently has 131 planning applications open, with a median wait of 39 weeks for review and 25 weeks for approval from submission.
These figures are computed from HRM's planning-application timestamps — submit, decision, and the live pre-decision queue — read each week.
Financing corner
The capital stack
The ACLP program provides up to 100% loan-to-cost construction debt, with terms extending to 2031-32. Additionally, MLI Select can reduce the mortgage-insurance premium by up to 30% and push amortization out to 50 years, both contingent on scoring for affordability, energy efficiency, and accessibility.
The explainer
What the pipeline number means
By stage: 21,002 units are under construction, 4,457 are approved and not yet started, and 2,800 are proposed.
SOURCES · Pipeline: Helio's development map; units under construction are the units in tracked projects at the construction stage, stalled projects included, in the issue's week. Rates: Bank of Canada published series. Supply/people/cost/programs: CMHC + StatCan (2026-06-23). The Halifax Brief is published by Helio Urban Development, a Halifax development company. Spotted an error? Correct a record.
Building or funding rental housing in Nova Scotia?
- ER-3 lot owners Up to eight rental units where the lot allows; the reading of your lot is free.
- Organisations with a mandate A building your organisation owns, pencilled under the programs in force; the mandate analysis first.
- Capital partners You own the building; Helio carries it from the lot to the first tenants.