Subdivision Costs & Timeline in HRM: From Dual ER-3 Lots to One 12-Unit Build

published on 20 August 2025

Combining two ER-3 zoned lots in Halifax Regional Municipality (HRM) offers a lucrative path to creating multi-unit rental properties. This process involves consolidating lots, navigating municipal approvals, and managing construction. Here's what you need to know:

  • Approval Process: Lot consolidation and planning approvals can take 10–12 months, including public consultations and council decisions.
  • Municipal Fees: Expect planning and building permit fees based on construction value. For a $1.92M project, fees total around $13,209.60, plus additional charges for plumbing, development permits, and infrastructure.
  • Construction Timeline: Traditional fragmented methods can take 12–18 months, while integrated design-build approaches promise faster completion (as short as 6 months) and cost certainty.
  • Budget Considerations: Fixed-price construction averages $160,000 per unit ($1.92M total), while CMHC MLI Select financing increases per-unit costs but offers better financing terms.
  • Rental Income Potential: Monthly rents per unit range from $1,950 to $2,100, generating up to $25,200 in monthly income for a 12-unit property.

Choosing an integrated construction approach can save time, reduce costs, and maximize returns. Efficient planning and understanding HRM regulations are essential for a successful project.

Unlocking NOVA SCOTIA Housing Growth: Challenges & Solutions

How to Combine Two ER-3 Lots in HRM

If you're planning to combine two ER-3 lots in Halifax Regional Municipality (HRM) for a 12-unit project, you'll need to navigate a planning application process that can take up to a year. Municipal approval is mandatory before breaking ground, so understanding the steps involved is key to keeping your project on track.

The process unfolds in two main stages: submitting the required documents and securing approval through public consultation. Below, we break down the essential details to help you plan effectively.

Application Process and Required Documents

Your first step should be contacting HRM's Planning and Development team at 902-490-4472 to arrange a pre-application consultation. This meeting is crucial for clarifying which documents you'll need and addressing any potential hurdles early on.

Once you're ready, submit all required documentation as specified by HRM. If you're unsure about the specifics, consider submitting a planning application inquiry through HRM's 311 Contact Centre. This pre-application stage can help pinpoint potential issues before you formally begin the process.

Approval Times and Municipal Contacts

The entire planning application process in HRM typically spans 10 to 12 months from submission to final approval [1]. However, the timeline can vary depending on the complexity of your project and the level of public interest it generates.

Public consultation is a key part of the process. Expect steps like site signage, online updates about your project, and notifications to nearby residents. In some cases, public meetings or surveys may be conducted, which could influence the timeline.

The final decision on your application will be made by your local Community Council after a public hearing [1]. Once approved, there is a 14-day appeal period during which affected parties can submit appeals to the Nova Scotia Utility and Review Board [1]. Once these steps are completed, you’ll be ready to move on to the building permit process.

To stay on top of your application, maintain regular contact with your assigned HRM planner. They can provide updates on the status of your application and flag any issues that need attention. Successfully completing the lot combination process lays the groundwork for a smoother experience when applying for your building permits.

Municipal Fees and Costs for 12-Unit Construction

When navigating the HRM multi-unit development process, understanding municipal fees is just as essential as managing permit applications. While HRM's fee structure is relatively simple, various factors can influence your overall costs. Notably, a provincial fee freeze introduced in October 2023 will remain in place until at least October 2025 [3].

Planning and Building Permit Fees

In HRM, building permit fees are calculated based on your project's estimated construction value. For a 12-unit residential building, the fee is $6.88 per $1,000 of the estimated construction value [2]. For example:

  • At $160,000 per unit (or $1.92 million total), the fee would be approximately $13,209.60.
  • A $2 million project would result in fees of about $13,760.
  • For a $1.5 million project, the cost would drop to around $10,320.

Additionally, plumbing permits are charged at $25 per unit, totalling $300 for a 12-unit project [2]. This fee covers the review and approval of plumbing plans and installations.

Development fees can vary depending on the nature of your project. For multi-unit residential buildings, a Commercial Development Permit Fee of $600 applies [2]. Site plan approval fees range from $600 for non-substantive approvals to $2,310 for downtown substantive approvals, depending on the complexity and location of the project [2].

All these fees must be paid when submitting your application, so it’s crucial to account for them early in your budgeting process [2]. These costs are a significant part of your pre-construction expenses, even before factoring in infrastructure-related fees.

Utility Connection and Infrastructure Costs

Utility connection costs represent a major portion of your infrastructure budget. Water and sewer connections are managed through Halifax Water, which applies Regional Development Charges (RDC). These charges are not included under the current fee freeze [2]. Similarly, Pavement Impact Charges are still in effect to offset road wear and tear caused by construction activities.

If your project involves parkland dedication or falls under incentive zoning provisions, expect additional costs. Fees for Parkland Dedication and Incentive or Bonus Zoning Public Benefits are specifically excluded from the provincial fee freeze [2].

Other upfront expenses include security deposits and liability insurance, which are necessary for project approval.

"We're concerned that we may not be able to continue on with grants for affordable housing." - Cathie O'Toole, Chief Administrative Officer for the Halifax Regional Municipality [3]

The fee freeze has resulted in HRM losing $9 million to $11 million annually in planning and development fee revenue [3]. However, Halifax Mayor Mike Savage has pointed out that HRM's development fees remain "among the lowest in Canada" [3].

For precise utility connection costs, it’s best to contact Halifax Water directly after your lot combination is approved. These fees can vary depending on your property's location, existing infrastructure, and capacity requirements. Taking this step early can help you avoid unexpected budget overruns during construction.

To confirm which fees apply under the provincial freeze, reach out to HRM's Planning and Development team at 902-490-4472. These municipal fees and infrastructure costs will play a key role in shaping your total project budget, which will be explored further in the next section.

Construction Timeline for 12-Unit Build

Building a 12-unit rental property in HRM with separate contractors for site preparation, structure, MEP (Mechanical, Electrical, and Plumbing), finishing, and inspections can be a logistical challenge. Delays caused by weather, scheduling conflicts, or coordination issues often stretch the timeline to anywhere between 12 and 18 months. Let’s explore how this fragmented approach compares to an integrated method that simplifies project delivery.

Construction Phases and Time Requirements

Integrated vs Fragmented Construction Methods

The main difference between these two approaches lies in how the project is managed and who takes accountability. A fragmented method involves hiring separate contractors for each phase of the project. While this might seem straightforward, it often leads to what can only be described as "coordination chaos." Delays in one phase tend to create a domino effect, pushing back the entire timeline.

On the other hand, an integrated design-build approach consolidates all trades under one management team. This eliminates inter-contractor delays and provides a single point of accountability, making the process much more efficient.

For example, Helio Urban Development guarantees a 6-month completion time for projects with four or more units. They back this promise with a fixed-price construction model and financial penalties of up to $1,000 per day for delays. The financial implications of such a compressed timeline are substantial. With each of the 12 units generating between $1,950 and $2,100 in monthly rental income, a faster build allows property owners to start collecting rent up to a year earlier. That’s an additional $280,800 to $302,400 in cash flow during the first year alone.

Beyond financial gains, Helio offers features like daily photo updates and real-time project monitoring. These tools give property owners full transparency without requiring constant site visits. This level of oversight reduces uncertainty, ensures projects stay on schedule, and provides financial predictability, allowing owners to transition to income generation faster.

For property owners in HRM, choosing between a fragmented, multi-contractor model and an integrated design-build approach can significantly impact both timelines and costs. The streamlined design-build model not only shortens the construction period but also ensures better cost control and a quicker return on investment - key factors for successful project execution in HRM.

sbb-itb-16b8a48

Cost Planning for Lot Combination and Construction

Turning two ER-3 lots into a 12-unit property in Halifax Regional Municipality (HRM) requires meticulous financial planning. Underestimating expenses can lead to budget shortfalls, potentially stalling your project.

Detailed Cost Breakdown

Combining lots in HRM comes with several mandatory municipal fees that need to be factored in early. Planning application fees range from $3,430 to $5,720, depending on the complexity of your proposal, and an additional $1,000 advertising deposit is required for these applications [4].

The subdivision process itself includes multiple stages, each with its own fees:

  • Concept fee: $700
  • Tentative fee: $480
  • Final subdivision fee: $600 if no new infrastructure is needed, or $2,310 if infrastructure upgrades are required [4].

These municipal fees are just the beginning. Other costs, such as subdivision securities, inspection fees, provincial filing costs, and Halifax Water fees, will add to the total as the application moves forward [4].

For construction, the costs vary based on the approach and quality of materials. A fixed-price construction model, at $160,000 per unit, offers budget predictability, bringing the total project cost to $1.92 million. This price typically includes features like ductless heat pumps, triple-pane windows, quartz countertops, engineered hardwood floors, and high-quality fixtures.

Alternatively, choosing CMHC MLI Select construction increases the cost to $200,000 per unit, totalling $2.4 million for 12 units. While this option involves a higher upfront investment, it allows for 95% financing, requiring only a 5% down payment, and offers 50-year amortization periods, which can significantly improve cash flow.

These financial decisions directly impact rental income potential. With rents ranging from $1,950 to $2,100 per unit, a 12-unit property can generate between $23,400 and $25,200 in monthly rental income. Many property owners find CMHC MLI Select financing beneficial for achieving positive cash flow from the start, while conventional financing typically yields annual returns of 12% to 20%.

With these initial costs in mind, managing unexpected expenses becomes a priority.

Controlling Construction Cost Overruns

Beyond fixed costs, keeping overruns in check is critical to staying within budget. Fragmented projects often exceed budgets by 30% to 60%, largely due to poor coordination between trades, leading to delays and frequent change orders.

A major culprit is the cost-plus pricing model used by many contractors. Under this model, property owners cover materials, labour, and a markup, often without knowing the final cost until the project concludes. In contrast, fixed-price contracts eliminate this uncertainty by locking in the total cost upfront. These contracts also shift financial risk to the construction company, ensuring better cost control.

Additionally, fixed-price contracts often include penalty clauses - up to $1,000 per day for delays - ensuring timely completion. With a 12-unit property generating up to $25,200 monthly, even a single month of delay can have a significant financial impact.

Quality control is another key factor in managing long-term costs. Engineer inspections at five critical stages of construction help prevent costly future repairs. A two-year construction warranty further protects property owners by covering any defects without additional expenses.

Choosing an integrated design-build approach with fixed pricing can save property owners an average of $47,000 in coordination inefficiencies compared to fragmented construction methods. These savings come from reducing duplicate site visits, cutting material waste, and avoiding delays typical of multi-contractor projects.

HRM Regulations and ROI Maximization

Navigating Halifax Regional Municipality's (HRM) regulatory framework plays a crucial role in determining your project's profitability. By leveraging efficient approval processes and construction strategies, property owners can reduce delays and maximize returns. Understanding this framework opens the door to streamlined construction methods that can significantly enhance your ROI.

Faster Approvals and Avoiding Delays

HRM's municipal planning strategy has shifted to prioritizing the rapid expansion of housing supply, driven by the ongoing housing crisis. This creates an environment where residential development approvals are often expedited, offering opportunities for property owners who can navigate the system effectively [5].

To accelerate residential development, HRM has introduced temporary measures that could save property owners considerable time and money. For example, on-site parking and unit mix requirements have been temporarily removed for residential buildings in urban service areas, provided construction begins before April 1, 2027 [5]. This change not only reduces parking infrastructure costs but also allows for greater flexibility in unit design.

Another advantage is the absence of maximum height restrictions in most zones, which means residential buildings can optimize density without artificial limits [5]. For instance, a 12-unit project on combined ER-3 lots can be designed to maximize rental income without being constrained by height regulations.

To avoid delays, it’s critical to engage experienced professionals who can ensure that all documentation - such as engineering reports, environmental assessments, and architectural drawings - is complete and accurately addresses municipal requirements. Incomplete or incorrect submissions often lead to extended timelines due to back-and-forth communications with municipal staff.

Additionally, properties requiring infrastructure upgrades may face longer approval times. Identifying these requirements early in the planning process allows for better budgeting and helps avoid unexpected delays. Efficient approvals lay the groundwork for a seamless transition into the construction phase, minimizing setbacks and keeping your project on track.

Higher ROI Through Integrated Construction

Once regulatory challenges are addressed, construction strategies take centre stage in driving profitability. Halifax's market conditions present strong opportunities for property owners who can execute projects efficiently. In 2023, multifamily property demand surged, with absorbed units increasing by 111% [6]. Furthermore, by February 2024, multifamily properties recorded the highest transaction volume across asset classes, totalling $114.6 billion [6].

However, rising costs pose a challenge. Operating expenses for multifamily properties increased by 28% year-over-year, with insurance costs alone jumping over 10% compared to 2022 [6]. Integrated design-build methods offer a solution by streamlining processes and reducing unnecessary expenses. Unlike fragmented approaches, integrated construction brings all aspects - design, engineering, and building - under one roof, ensuring accountability and eliminating coordination inefficiencies.

Incorporating technology during construction can also improve long-term returns. Properties equipped with smart home features and energy-efficient systems often command higher rents and see lower tenant turnover. Satisfied renters are nearly twice as likely to cite property management as a reason for renewing their lease when technology meets their needs (50% compared to 27%) [6]. These features not only enhance tenant satisfaction but also contribute to higher retention rates.

The quality of construction directly impacts tenant experience and ongoing expenses. Nearly half of dissatisfied renters cite "looking for a superior property manager" as a reason for moving, but the underlying quality of the building - such as reliable plumbing, consistent heating, and durable finishes - plays a significant role in tenant satisfaction [6]. High-quality construction reduces maintenance calls and tenant complaints, keeping operational costs in check.

Energy-efficient construction methods also offer long-term financial benefits. For instance, properties using Ratio Utility Billing Systems (RUBS) have seen water consumption drop by up to 27% [6]. Combined with energy-efficient building designs, these systems help property owners manage utility costs while offering tenants predictable expenses. These features not only lower operational costs but also shorten the timeline to profitability.

Construction delays can have a significant financial impact. For a 12-unit property with potential monthly rental income of $23,400 to $25,200, each month of delay represents substantial lost revenue. Opting for integrated construction methods with guaranteed timelines protects this income stream, ensuring your project generates returns as planned.

Finally, fixed-price contracts provide cost certainty, allowing for accurate ROI calculations. This predictability simplifies financing decisions and enables more precise investment planning. By combining regulatory efficiencies with integrated construction strategies, property owners can unlock the full potential of their investments.

Conclusion: Streamlined Multi-Unit Development in HRM

Developing a 12-unit rental property by combining two ER-3 lots in HRM requires precise coordination across subdivision processes, municipal approvals, and construction execution. Success hinges on a solid understanding of local regulations and choosing construction strategies that minimize risks.

Once you've completed the planning and fee assessments outlined earlier, the next critical step is submitting a consolidation application with accurate documentation to ensure compliance with HRM regulations. This aligns your project with the municipality's priorities, as outlined in HRM's Regional Plan, which aims to direct 75% of new housing growth to urban areas already supported by municipal services. This focus on urban growth can lead to faster approvals and better access to infrastructure [9].

Incorporating infrastructure charges and municipal fees into your budget is essential to avoid financial surprises. However, even the most carefully planned budgets can be derailed by construction delays and cost overruns, which are all too common with traditional building methods. Budget overruns can range from 30% to 60%, and project timelines can stretch from 8 months to over 18 months.

An integrated design-build approach offers a solution to these challenges. By bringing together planners, architects, engineers, and construction teams under one contract, this method ensures fixed pricing and guaranteed timelines. This not only protects your budget but also secures your rental income stream. For example, Helio Urban Development has demonstrated how this approach can deliver fixed-price construction at $160,000 per unit within just 6 months, even including penalties of up to $1,000 per day for delays. Their streamlined process tackles common issues like coordination problems, budget overruns, and timeline extensions.

These strategies align well with the evolving regulatory landscape in HRM. Recent updates to the Regional Municipal Planning Strategy, the Regional Subdivision By-law, and the introduction of new Minimum Planning Requirements by the province are reshaping the development process [7][8][9]. Staying informed about these changes and working with seasoned professionals can help you navigate potential hurdles.

FAQs

What are the advantages of using an integrated design-build approach for developing a 12-unit rental property in HRM?

An integrated design-build approach simplifies the process of creating a 12-unit rental property in HRM by bringing design and construction together under one team. This collaborative method offers some major perks, including smoother communication, quicker timelines, and tighter control over costs.

With just one team handling everything, you can sidestep the delays and miscommunication that often come with more traditional, segmented approaches. Plus, since the design and construction teams work hand in hand, the project stays aligned with your budget from day one, minimizing unexpected costs. For property owners in HRM, this means a more seamless experience, fewer hiccups, and a faster journey to the finish line.

What impact does HRM's provincial fee freeze have on the cost of developing a multi-unit property, and which fees still apply?

The provincial fee freeze in HRM provides a temporary break from municipal development charges for two years, giving property owners some financial relief. However, it's important to note that not all fees are eliminated. For instance, permit fees - ranging from about $25 to $50 per unit for multi-unit projects - still apply.

While this freeze can lower overall costs, developers should account for other expenses like building permits, inspections, and regulatory requirements. Being aware of these remaining fees is crucial for accurate budgeting and keeping the development process on track.

How can property owners in Halifax Regional Municipality combine two ER-3 lots for a 12-unit building smoothly?

To merge two ER-3 lots in Halifax Regional Municipality (HRM) and navigate the approval process smoothly, your first move should be to consult with HRM Planning & Development. They’ll help confirm if your project is feasible and guide you through the applicable zoning requirements. Once that’s clear, you’ll need to submit a formal subdivision application, ensuring it aligns with HRM’s zoning and land-use policies.

Take the time to review the Regional Centre Land Use By-Law and other related planning documents. These resources will help you understand any specific restrictions or requirements that might affect your project.

It’s also a good idea to engage with municipal planners early on. By addressing potential challenges upfront, you can avoid unnecessary delays and keep the process on track. Careful preparation and adherence to municipal guidelines are essential for a successful application.